Saturday, July 24, 2010

electrical, some plumbing & heating 07/07/10

1) this is placed in hallway between kitchen and master bedroom, this is where the filter will go.

2) piping in butler's pantry. There is a sink.

3) piping in Kitchen.

4) Crawl space in ceiling to the attic.

5) All air vents will be in the ceiling instead of on the floor.

6) Dining room/ Kitchen area.

8) Piping for utility room. red for hot water/ blue for cold water, duh!! :P

9) heating unit in the ceiling.

10) more wood bracings and heating unit in ceiling.

11) the microwave will be placed where the silver casing is.

12) Light casing.

13) breaking in garage.

14) electricians helper.


15) breaker.

Roof starts, Shingles and Windows are placed!! 07/07/10

1) framing of roof

2) framing of roof

3) framing of roof

4) framing of roof from inside...the house's spine!

5) Hallway towards master bedroom with a partial roof coving.

6) framing of roof.

7) framing of roof over garage.

8) framing of roof over foyer.

9) framing of roof partial cover.

10) framing of roof with partial cover.

11) framing of roof with partial roof.

12) kitchen window, back porch area, framing of roof

13) roof covering almost finished.

14) roof covering almost finished.

15) framing roof and partial roof covering.

16) roof framing over garage.

17) front door, front porch covered, shingle supplies on top.

18) windows are in!!!

19) total covering now.

20) Hallway towards master bedroom with total roof cover.

21) sky-light between dining room and great room.

22) Partial shingles and windows.

23) partial shingles.

24) Partial shingles.

25) Honor and her rock Pizza - goodbye teeth!! lol

26) partial shingles and more supplies.

27) Shingles are FINISHED!!! Whooo hooo!

28) Shingles finished over front door area.

29) Shingles finished.

30) Special ordered bathtub, 6ft long and 4 foot wide!! oh yeah!


31) Mark standing infront of our new bathtub!!

Floor and Walls start - 07/04/10

1) Garage

2) Very large windows, all windows in the house are this size, except for in the kitchen.

3) "X" marks the spot. This is how you get down to the 2ft crawl space.

4) Butler's Pantry, this is part of the kitchen area.

5) Kitchen area...Honor is standing where the sink will be.

6) Island in kitchen. the other side can be a breakfast bar.

7) Foyer, the first thing you see when you go through the front door.

8) outside of house.

9) outside of house...Honor was excited!!

10) Looking at family room from the garage area.

11) utility room & master bathroom from the garage.

12) Family room

13) Looking through the front door towards one of the bathroom areas.

14) Front door

15) Honor & Mark looking through the large window for the first time!!


16) YAY!! IT'S FINALLY STARTING!!